Staged Construction Inspection Pricing Page

 

Note: Additional fees maybe applicable if non standard items / additional stages are required. Confirmation once building plans are sighted. You will be able to select several stages on the next page. Simply click a “Book Now” button to move forward.

SLAB INSPECTION

CARRIED OUT ONCE SLAB HAS BEEN LAID

$445

Slab Dimensions

Slab Thickness


Footing dimensions


Plumbing and electrical pre-lay location on slab

Cracking (acceptable)

Step down to wet areas

Parging

Level

Finish

PLATE HEIGHT INSPECTION

WALLS FULLY BUILT

$445

Window and door frames installed plumb and square

Window and door frames are in teh correct location within reason as per plans.

Flashings and Weep holes installed.

Room dimensions and openings are of similar size to approved plans

Wet area rooms are square.

If possible check that lintels have a minimum bearing

If possible check that brick lintels have a minimum bearing

Brick work bonding and sufficient mortar in place

Workmanship facebrick.

Wall Heights

Cavity dimensions and clean.

Wire tie spacing.


Window ties/straps.

Stiffening columns

Site welding.

Insulation.

Walls are ready for next trade.

Holding down straps and tie down points installed.

Other timber/steel frame and/or composite wall system (Masterwall).

ROOF FRAME INSPECTION

BEFORE ROOF COVERING IS INSTALLED

$445

Holding down straps and tie down points fixed to roof frame. 

Ceiling Joists

Ceiling Joist Trimmers

Hangers

Counter beams. 

Timber/Metal roof battens

Ridge

Rafters

Under-purlins 

Struts

Collar ties

HANDOVER/PCI INSPECTION

BEFORE YOU SIGN ACCEPTANCE

$595

Roof Tiles: installation, fixing-centres

Adequate use of pointing - hip and ridge tiles.

Roof Sheeting: fixing, including ridges and hips.

Penetrations.

Gutters joins, clips.

Downpipes location, joins, spacing and clips.

Windows

Labelling and safety markings

Windows: labelling safety markings, restricted opening two story.

Location and number of Smoke Alarms and RCD's

Fire Separation: Separating walls underside of roof covering.

Wet area and external balcony waterproofing: floor wall junctions, penetrations in shower, bath to wall, floor wastes

Wall and floor tiling: Workmanship, corner joints, adhesion, falls to floor waste.

Hot and cold tap operation. Drains clearing as expected.

Operation of plumbing fixtures. i.e. toilet.

Shower screens and mirrors: Workmanship, fixings.

Light points. Power points.

Kitchen Appliances basic functions.

Air Conditioning: Cold and Hot operation.

Ventilation: exhaust fan and Rangehood ducted to outside air.

Stairs: riser and going dimensions.

Balustrade: structure and handrails. Height and spacing.

Insulation: Sarking and ceiling insulation.

Internal plaster: Set – hardness, curing and workmanship.

External render/acrylic: Ground level finish and workmanship.

Ceilings and wall plasterboard linings: Fixings, back blocking, workmanship and cornices.

Cabinets: Workmanship, Fixings, Install level and plumb. Penetration sealing. Bench top sealing. Rangehood distance from hotplate.

Fixing carpentry: Internal and external doors: gaps/alignment. Door furniture. Skirtings and architraves.

Paving: Concrete/brick – workmanship, edge restraint, steps and falls.

Patio/pergola – other exterior structures. Workmanship.

Fences and gates: Workmanship.

Garage door: Operation.

Garage door: Operation.

Stormwater drainage: connection to downpipes.

Retaining walls.

Termite durable notice: Installation of notice.

suspended slab inspection

For double storey homes

$445

Slab dimensions 

Slab thickness

Upturn / downturn beam dimensions 

Plumbing and electrical pre-lay location on slab.

 

 

Have a question? Please contact us